We are building a 1,000 sqft addition to our office/showroom to serve you better.
(Click on the thumbnails for a bigger view. Use your browser's "back" button to return to this page)

August 10, 2015 - Construction for the 1,000 sqft addition to our office/showroom has begun.

August 14, 2015 - The grade beam and piles are being poured
 

August 26, 2015 - The concrete slab has been poured and is now curing. Framing will start in a few weeks.

September 18, 2015 - The crane is waiting to lift the trusses in place

September 19, 2015 - framing is done, ready for sheathing

September 23, 2015 - sheating is well under way

September 25, 2015 - sheating almost completed
 

September 28, 2015 - ready for roofing
 

 

October 5, 2015 - roofing is done, window frames are in. Prep for finishing the exterior is under way.

October 16, 2015 - doors and windows are in, stucco is under way

October 22, 2015 - stucco is up, soffits are finished and the feature pergola at the showroom entrance is completed.

February 1, 2016 - with the outside completed, winter is a good time to finish the inside.

February 1, 2016 - view from the showroom into the office addition

February 1, 2016 - view from the office back towards the hallway to the showroom.

February 1, 2016 - a typical workstation setup.